On 21 August 2019 our new photovoltaic system was connected to the grid for the first time.
Currently 2112 photovoltaic panels with an engergy of 295 W per panel are installed on the roof of the CAP PARTS AG.
The system has a power of 623 kWp and according to the predicted specific value it should generate enegy of 560.000 kWh per year.
In order not to have only a peak of production at midday, not all panels were aligned towards the south, but also in east-west orientation.
That leads to a lower peak value at midday, but to a higher in the morning and the afternoon. This represents from the point of view of reducing the load profile of the consuption
the most economical and sustainable option.